Owner: Massachusetts Port Authority

Partner: SPS New England

Location: Boston, Massachusetts

Project Overview:

  • Drove (36) 30” OD x 1” thick pipe piles, mainly from a barge, to construct the bridge foundations spanning the Reserved Channel.
  • Installed (18) 20” diameter pipe piles for the new bridge abutments on each side of the Reserved Channel.
  • Constructed various excavation support structures for the project.